In
Dunlop v New Garage & Motor Co the plaintiffs supplied the defendants with
tyres under a contract designed to achieve resale price maintenance. The
contract provided that the defendants had to pay Dunlop £5 for every tyre they
sold in breach of the resale price agreement. When the garage sold tyres at
less than the agreed minimum price, they resisted Dunlop’s claim for £5 per
tyre, on the grounds that it represented a penalty clause. On the facts of the
situation, the court decided that the provision was a genuine attempt to fix
damages and was not a penalty. It was, therefore, enforceable.
In
deciding the legality of such clauses, the courts will consider the effect,
rather than the form, of the clause, as can be seen in Cellulose Acetate Silk
Co Ltd v Widnes Foundry Ltd In that
case, the contract expressly stated that damages for late payment would be paid
by way of penalty at the rate of £20 per week. In fact, the sum of £20 was in
no way excessive and represented a reasonable estimate of the likely loss. On
that basis, the House of Lords enforced the clause, in spite of its actual wording.
In Duffen
v FRA Bo SpA it was held that a term in an agency contract which established
so-called ‘liquidated damages’ for the dismissal of the agent at £100,000 was,
in fact, a penalty clause and could not be enforced. This was in spite of the
fact that the agreement specifically stated that the £100,000 was ‘a reasonable
pre-estimate of the loss and damage which the agent will suffer on the
termination of theLtd v agreement’. In reaching its conclusion, the court held
that although the wording of the agreement was persuasive, it was outweighed by
the fact that the level of damages did not alter in proportion to the time
remaining to be served in the agreement. The claimant was consequently only
allowed to claim for normal damages, although these could be augmented under
the Commercial Agents Regulations 1993
The
whole question of penalty clauses is fraught. It is obviously advantageous, in
a business context, for the parties to a contract to know with certainty what
the financial consequences of any breach of the contract will be, so as to
allow them to manage their risk properly. However, the possibility of the
courts subsequently holding a damages clause to be punitive introduces the very
uncertainty that the clause was designed to avoid.
In
any case, why should businesses not be bound by clauses, as long as they have been
freely negotiated? This point leads to a comparison of liquidated damages
clauses and limitation and exclusion clauses. Usually, penalty clauses are
thought of as overestimating the damages, but it should be considered that such
a pre-estimation may be much lower than the damages suffered, in which case the
clause will effectively operate as a limitation clause. It would surely be
better all round if the liquidated damages/penalties clause question was
subject to a similar regime as regulates exclusion/limitation clauses under the
Unfair Contract Terms Act 1977. The courts would then be required to examine
whether the clause was the product of truly free negotiation and not the
outcome of an abuse of power, in which case it would be effective, or,
alternatively, whether it was imposed on one of the parties against their wishes,
in which case it would be inoperative.
0 comments:
Post a Comment